Workflow · Quantities and carbon
Quantity take-off
Ask for the quantities of an IFC model and get them by element type, storey and material, measured from the solids with the openings cut and set beside the authoring program's own figures. On the Zurich office, an Archi sample model: 5,924 m³ over 9,899 elements in 89.1 s.
5,924 m³ net of 153 door and window openings, 9,899 elements · Zurich office
843.6 m³ walls, the same as Revit's figure
827.9 m³ roof, the same as Revit's figure
0 elements left unmeasured
89.1 s to compute
What was checked
All 9,899 building elements of the Revit 2027 IFC export. Volumes from the IFC solids with the 153 door and window openings cut; the site terrain is left out of the totals. The file has no IFC base quantities, so Revit's own Dimensions property sets were read per element type as the declared figures to compare with.
5,924 m³ · building volume net of 153 openings, 9,899 elements by type, storey and material
Steps, as the assistant ran them
- ifc_job_submit
Ran quantities on the Zurich office IFC: 9,899 elements, 5,924.0 m³ net of 153 openings, by type, storey and material, with Revit's declared figures beside them, in 89.1 s.
Tool chain
ifc_job_submit
Programs in this workflow
- IFC · The open IFC model the tools read, check and write
- Quantities and carbon · Computes quantities and embodied carbon from the IFC
Method
Archi Automate measured every element from its IFC solid, with the door and window openings cut, and listed the declared Revit figure beside it where the file has one.
By type: slabs 16, 3,449.4 m³ (Revit 3,443.4 m³, the difference is the landings); walls 277, 843.6 m³ (Revit 843.6 m³); roof 1, 827.9 m³ (Revit 827.9 m³); glulam beams 143, 268.6 m³; curtain panels 2,500, 183.8 m³; glulam columns 66, 181.9 m³ (Revit 181.9 m³); mullions 6,580, 134.4 m³; stair flights 20, 20.7 m³; doors 110, 12.2 m³ (Revit 11.2 m³); railings 22, 1.6 m³.
By storey: L00 1,613.0 · L01 696.5 · L02 696.3 · L03 695.6 · L04 726.6 · L05 656.9 · Roof 839.1 m³. By material: concrete 3,636.0 m³, screed 862.9 m³, partitions 615.9 m³, glulam beams with no material 268.6 m³, glulam 181.9 m³, glass 167.0 m³, aluminium 151.2 m³, cast-in-place concrete 26.7 m³.
Limits
- Volumes come from the IFC solids, so they are as good as the model: the mullions and spandrels are modelled as solid aluminium bars and plates.
- Declared areas are compared per element type only; they are not added up across types, because they measure different things.
- The recorded run used an Archi Automate development build; the tools it calls are in the released version.
- The Zurich office is an Archi sample model, not a built project.